Let us start by building a summary based on when
our tasks and activities will occur.
1) Open your My Summer Holiday map.
2) Browse into the "Getting on the Plane" sub
topic and select the "Pickup tickets & vouchers" topic, right-
click and choose "TPAssist Journal"
3) Uncheck "Level Topic's Dates", check the box
next to Start and then click Ok.
4) Now, select "Pack the bags", right-click and
choose "TPAssist Journal".
5) Uncheck "Level Topic's Dates", check the box
next to Start and then use the date picker to change the date to
the next business day and then finally click Ok.
You
should now have a task tree that looks something like the
following:
Now
let us build the summary tree.
6) Choose the central topic, in the export
toolbar at the bottom of the window, choose the TPAssist icon, then
choose the "Tree Update" tab, Now choose "All" in the scope. (In
MindManager 7, just choose "Summary" from the TPAssist
Ribbon Tab)
7) Now click "Summary", then click OK.
Your
summary tree should now look something like the
following.
Notice
how each topic has a link. These links take you directly to
the topic for which the summary relates.